Knowledge

Rail Breakage Common Temporary Fixing Techniques

Temporary Fixing Techniques
Temporary Rail Repair Solution

1

 

Rail Breakage

Use Rail Clamps or Fishplates: Install temporary joint bars or clamps to hold the broken rail sections together.

 

Secure with Bolts: Tighten bolts to ensure the connection is stable.

 

Reduce Speed Limits: Implement slow-speed restrictions for trains passing over the repaired section.

Crane Rail Joint Bar

2

 

Track Misalignment

Realign the Track: Use hydraulic jacks to lift and reposition the rails to their correct alignment.

Stabilize with Ballast: Add temporary ballast to hold the track in place.

Check Gauge: Ensure the track gauge (distance between rails) meets safety standards.

Rail Clip For Railway Fastener

3

 

Ballast Washout or Sinking Track

Add Temporary Ballast: Fill the affected area with fresh ballast to stabilize the track.

Compact the Ballast: Use hand tools or portable equipment to compact the ballast and ensure stability.

Railway Base Plate For Railroad Fastening

4

 

Damaged Sleepers (Ties)

Replace with Temporary Sleepers: Install temporary wooden or composite sleepers to support the rails.

Secure Rails: Reattach rail fasteners to the new sleepers.